Divider

The Pedestrian pavement past OP4

Posted: 18th June 2026

Work in underway to create a walking route to the Horsed Keynes Booking Office

As part of the scheme to relay the roadway up to the car park at Horsted Keynes, a pedestrian route is being laid out the provide a route the the Booking Office. This will define the edge of the road when it comes to re-tarmacing it. Considerable effort has gone in to surveying the road to get the optimum levels to minimise the amount of tarmac to be used. The initial work is to set the edge of the path on the OP4 side.

The excavated path looking towards the exit  The excavated pathway looking towards the booking office

Left: The excavated pathway looking towards the exit

Right: The excavated pathway looking towards the Booking Office

 

Left: The base for the path is being laid

Right: The edging stones are set into lean mix

All images: Bruce Healey

Memorial Plaque to Bob Saill

Posted: 14th May 2026

A memorial plaque has been placed on the East Grinstead water tower

Bob “The Builder” Saill was a long standing volunteer of the Infrastructure team who sadly passed away in 2025. He was involved in many building projects including improving the brickwork on the piers of the Imberhorne Viaduct and the OP4 carriage shed at Horsted Keynes. While much of this work is unseen by our visitors, the water tower at East Grinstead is the most obvious showpiece of his excellent work. A plaque has now been placed on the water tower to commemorate Bob and his work.

Bob building the East Grinstead water tower  Bob's plaque

Left: Bob Saill during construction of the East Grinstead water tower (image: Brian Kidman)

Right: The plaque on the water tower (image: Andy Plamer)

Loco Yard No 5 Road and Loading Bay railings

Posted: 4th May 2026

Recent work at Sheffield Park

Route of new tram raod

The alignment of the new loco shed at Sheffield Park meant that the new engine shed road was not connected to the old tram road (which runs past the Above Workshop Facility). The long term plan is to connect the two loco sheds as can be seen from the image to the right. The tape shows the intended line of the new tram road. This work will be split into phases. The first phase, a single 60 foot panel of track, has now been completed and can be used as a loading/unloading area.

The first task was to break out the concrete round the old tram road. The old track could then be removed, new tack laid and, with suitable shuttering, the new road concreted in. Other phases to follow when time and finances permit.

Work also undertaken during this period was the erection of railings on the loading bay at Sheffield Park.

Breaking out the old concrete

Left – Breaking out the old concrete (Bruce Healey)

Right – Image from 2022 showing intended line of new tram road (Jon Goff)

Old tram road exposed         Old tram road removed

Left – Old track exposed (Bruce Healey)

Right – Old tram road removed (Bruce Healey)

80151 trying out the new road

Above: 80151 trying out the new road (Jon Goff)

Concrete laid Loading bay railings being assembled

Left – Concrete laid (Jon Goff)

Right – Loading bay railings being assembled (Bruce Healey)

Horsted Keynes Siding Renewal

Posted: 19th February 2026

Work starts on 'minus 2' road

‘Minus 1’ road is the siding nearest to Horsted Keynes Platform 1. This was relaid prior to the Rail 200 exhibition. However, due to shortage of suitable rail at the time, the siding was shorter than required and also had a short panel of Brighton standard 96lb bullhead rail whereas the rest of the siding was the standard 95lb. With more rail available (as discussed below), the 96lb panel was replaced and another added. The result can be seen in the image below although the ballast is still to be applied.

‘Minus 2’ road (obviously the siding adjacent to ‘minus 1’ road) is in need of replacement as the sleepers are in poor condition. The siding is to be relaid using concrete bullhead sleepers recovered a few weeks ago from the Ketches relay and 95lb bullhead recovered from the late 2025 Black Hut relay. Note that the rail from Ketches is old 96lb Brighton bullhead and the wooden sleepers from the Black Hut relay are mostly scrap although better ones have been reserved to provide a stock to replace sleepers on the running line as required.

At the time of writing this, the track in ‘Minus 2’ road is being removed. The image below shows the rail cutter. The powerful hydraulic cutters snip the rails in seconds. The scrap rail needs to be in 15 ft sections for easy transportation. The money recovered from the scrap value of the metalwork will go towards ballast (the mountain of ballast donated by HS2 has already been used up).

Minus 1 road replacement panels  Rail Cutter

Left: ‘Minus 1’ road completed except for ballast

Right: The rail cutter. The cutter is only used when scrapping rail, it gives a very rough edge as can be seen on the far rail.

Images: Bruce Healey

Ketches Relay Progress

Posted: 12th February 2026

.. nearly complete

Relay early complete The image to the right, taken on Saturday 7th February during a track patrol, shows the south end of the relay. All of the sleepers are down with some rail remaining which would be put in on the following Monday.

The images below were taken on the following Wednesday.

With the track joined up, some ballasting has taken place. More ballast was added during the day both between the rails and to the shoulders. The ballast at the shoulders helps to keep the formation in place and reduces and tendency to slip sideways.

Later in the day, the tamper was in action. Tamping raises the track and vibrates ballast under the ends of the sleepers. Having done this, more ballast is required as the apparent level of the ballast has reduced.

Remaining tasks are to tidy up the site and to improve the drainage on the east side. Note that the bulk bags visible were used to transport the base layer of ballast to side and now hold rubbish and other empty bulk bags.

The images below show the various stages during the day.

Side drop

 

Above and below: Side drop ballasting

Side drop ballasting

Tamper  Close up of tamper

Left: The tamper in action

Right: Close up of tamper lifting the track with the tines deployed and vibrating

All images: Bruce Healey

Ketches Relay Under Way

Posted: 6th February 2026

.. despite the rain

The Ketches 2026 relay will go down in Infrastructure history as one of the wettest ever. The often torrential rain was present on all except one day.

Taking place in a cutting, the usual terram, plastic. terram sandwich was required to ensure that the new formation would be dry. The cutting has long suffered from boggy conditions and an insufficient bed of good quality ballast which was why there was a long standing speed restriction on this section of the line which will soon be removed.

The images below were taken on the one dry day of the entire relay.

Teream, plastic, terram saandwich  Ballasted track bed

Left: At the south end of the relay, the terram, plastic, terram sandwich can be seen

Right: The new track bed. There is a new drain on the near (west) side which has already been covered up.

Soggy  Sleepers being laid

Left: Taken from the east side, the condition of the ground can be seen and the quantity of recent rain is evident. One of the last actions of the relay will be to put in a functioning drain on this side to complement the one put in on the west side.

Right: The first sleepers have been laid

Sleepers being laid  

Left: More sleepers are lifted into position

Right: The end of the day

All images: Bruce Healey

Replacing the Sheffield Park Ground Frame

Posted: 16th January 2026

Motorising the access to the yard

The Sheffield Park ground frame which controls access to the loco shed is being replaced by a motorised system. This requires extending some track circuits, replacing the timbers under the relevant points and adding the point motors. The opportunity is also being taken to replace some old 96lb bullhead rail with 95lb bullhead recovered from track relays. The replacement rail is worn but easily in good enough condition for use in a siding.

Old ground frame  Ground frame indicators

Left: The partly dismantled ground frame

Right: The dismantled ground frame indicators

New point motor  96lb rail removed

Left: Point motor mounted but not yet connected. A terram, plastic, terram sandwich sits under the point timbers

Right: The 96lb rail has been removed to be replaced with 95lb

All image: Bruce Healey

Divider